Project Start: Tue 3/1/11
Project Finish: Mon 3/27/13

Microsoft Office Project Image

    Tasks  

ID
Task Name
DurationStartFinishDeadline
0
JSF_2_2_WORKING_SET~140
509 days?Tue 3/1/11Wed 3/6/13NA
41
2.2 Sprint 13 Faces Flows, HTML5
48 days?Wed 5/16/12Fri 7/27/12NA
42
730-Add elements to faces-config schema for in-view fdl
1 dayFri 7/27/12Fri 7/27/12NA
43
949-WindowId send cleanup request to EG
1 day?Thu 5/17/12Thu 5/17/12NA
44
971-MultiTemplating write proposal to EG
1 dayThu 5/24/12Thu 5/24/12NA
45
971-MultiTemplating prototype
1 day?Thu 5/24/12Thu 5/24/12NA
46
1089-Dataxxx Attributes
2 daysWed 5/16/12Thu 5/17/12NA
47
533-ConfigurationAsDOM
1 dayWed 5/30/12Wed 5/30/12NA
48
Deliver Expert Group Draft in lieu of PRD
0 daysFri 7/27/12Fri 7/27/12NA
49
Account for Java EE 7 Replan
33 daysFri 7/27/12Tue 9/11/12NA
50
Schedule adjustments
20 daysFri 7/27/12Thu 8/23/12NA
51
Prepare for JCP EC meeting
13 daysFri 8/24/12Tue 9/11/12NA
52
2.2 Sprint 14 HTML5 in shape for JavaOne
4 daysWed 9/12/12Mon 9/17/12NA
53
1111-Pass Through Elements: Merge Frank's prototype work
4 daysWed 9/12/12Mon 9/17/12NA
54
1075-Metadata
3 daysWed 9/12/12Fri 9/14/12NA
55
991-Input HTML5 attributes
2 daysWed 9/12/12Thu 9/13/12NA
56
Sprint 15 Plan JavaOne EG Draft Release
6 days?Tue 9/18/12Tue 9/25/12NA
57
Incorporate work from EG on 1160-ClearInputValues
3 daysTue 9/18/12Thu 9/20/12NA
58
Collect completed issues
2 daysTue 9/18/12Wed 9/19/12NA
59
Update spec
3 daysThu 9/20/12Mon 9/24/12NA
60
Release on java.net spec area
1 day?Tue 9/25/12Tue 9/25/12NA
61
Sprint 16 FacesFlows in shape for Public Review
2 days?Mon 10/8/12Tue 10/9/12NA
62
Faces Flow parameters
1 day?Mon 10/8/12Mon 10/8/12NA
63
Specification for Navigation Handler
1 day?Tue 10/9/12Tue 10/9/12NA
64
Sprint 17 Multi-Templating in shape for Public Review
1 day?Wed 10/10/12Wed 10/10/12NA
65
Reactivate EG discussion
1 day?Wed 10/10/12Wed 10/10/12NA
66
Sprint 19 HTML5 In shape for Public Review
1 day?Thu 10/11/12Thu 10/11/12NA
67
Clean up from JavaOne push
1 day?Thu 10/11/12Thu 10/11/12NA
68
Sprint 20 Public Review Release
2 days?Fri 10/12/12Mon 10/15/12NA
69
Collect completed issues
1 day?Fri 10/12/12Fri 10/12/12NA
70
Update spec
1 day?Mon 10/15/12Mon 10/15/12NA
72
Back End JCP Tasks
213 daysWed 4/18/12Wed 3/6/13NA
73
Date Adjustment
120 daysWed 4/18/12Fri 10/26/12NA
74
Public Review First Draft to Expert Group
0 daysFri 10/26/12Fri 10/26/12Wed 10/31/12
75
Expert Group Reviews PR Draft
5 daysMon 10/29/12Fri 11/2/12Tue 11/6/12
76
Public Review Released to JCP
0 daysFri 11/2/12Fri 11/2/12Fri 11/9/12
77
Public Review posted on JCP site
7 daysSat 11/3/12Fri 11/9/12Wed 11/14/12
78
Public Review
30 daysSat 11/10/12Thu 12/13/12Thu 1/3/13
79
Public Draft Specification Approval Ballot
14 daysFri 12/14/12Wed 1/2/13Fri 1/4/13
80
Prepare Proposed Final Draft
12 daysThu 1/3/13Fri 1/18/13Wed 1/23/13
81
Proposed Final Draft to EG
0 daysFri 1/18/13Fri 1/18/13Wed 1/23/13
82
Expert Group Reviews PFD Draft
13 daysMon 1/21/13Wed 2/6/13Sun 2/10/13
83
Final Draft Released to JCP
3 daysThu 2/7/13Mon 2/11/13Mon 2/18/13
84
JCP initiates Final Approval Ballot
3 daysTue 2/12/13Thu 2/14/13Thu 2/21/13
85
Final Approval Ballot
14 daysFri 2/15/13Wed 3/6/13Wed 3/27/13

     


     